Contents of Daily Log/Site Diary
Construction daily logs should include detailed information about various aspects of the project and site conditions. While the specific contents may vary depending on project requirements, the following elements are commonly recorded:
Project Details
Include the project name, location, contract number, and any other relevant identification information.
Date and Weather Conditions
Record the date of activities and note the prevailing weather conditions, such as temperature, precipitation, wind speed, etc. This helps identify weather-related impacts on the project.
Personnel
List the names and roles of personnel involved in the activities on-site, including workers, supervisors, contractors, and visitors.
Work Performed
Describe the tasks, activities, and milestones achieved during the day, including progress updates, completed stages, and any changes to the project plan.
Equipment and Materials
Document the usage of equipment, machinery, and materials, including quantities, delivery details, and any issues or delays related to their availability.
Safety Observations
Note any safety incidents, near misses, or potential hazards observed during the day. This helps prioritize safety protocols and address risks promptly.
Delays and Issues
Record any unexpected delays, disruptions, or issues encountered during the construction process. This includes weather-related delays, material shortages, equipment breakdowns, or any other significant events affecting progress.
Visitors and Meetings
Document any site visits, meetings, or discussions held with clients, consultants, inspectors, or other stakeholders.
Attachments
Supplement the written entries with photographs, videos, sketches, or other relevant documents that support the recorded activities or observations.